10 exam-style questions with answers and explanations, straight from our 1,030-question bank. Tap an answer to check yourself. When you're ready, take the scored version in the free practice test.
These 10 free CBCP questions are organized by exam domain, so you can see how each part of the Certified Business Continuity Professional blueprint is tested. Reveal the answer and explanation under each question.
Domain 1: Program Initiation and Management
Question 1
For a LEED v4 BD+C project, the enclosure-related OPR, Basis of Design, and design review have been completed under Fundamental Commissioning and Verification. The owner adds the envelope commissioning option under Enhanced Commissioning. What added work distinguishes this option from the enclosure work already completed?
Show answer & explanation
Correct answer: B - Carry enclosure verification into construction and occupancy, including the specified field performance tests.
Domain 2: Risk Assessment
Question 2
At design review, the Owner's Project Requirements call for continuous chilled-water circulation while either pump or its drive is removed for maintenance. The Basis of Design provides two full-duty pumps operated alternately through one shared variable-frequency drive, with no bypass or alternate drive. The commissioning review should identify which issue?
Show answer & explanation
Correct answer: C - The shared drive creates an OPR conflict that the designer must resolve.
Question 3
Two independent air-handling units are scheduled for functional testing. AHU-1 has completed all readiness checks. AHU-2 lacks the sensor-calibration verification required before its temperature-control tests. The units share no controls or equipment, and neither has a safety defect. To preserve as much valid testing as possible, how should today's schedule be adjusted?
Show answer & explanation
Correct answer: A - Test AHU-1 as planned; defer AHU-2's temperature-dependent tests until calibration is verified.
Question 4
The training specification requires operators to recover a pump system after a simulated power interruption and return it to automatic operation without leaving overrides. The installed sequence has passed functional testing. All operators attended the vendor's class and passed its written quiz, but they cannot complete the recovery exercise. Which evidence would close the outstanding training requirement?
Show answer & explanation
Correct answer: D - An observed successful recovery and restoration exercise after targeted instruction on the installed system.
Domain 3: Business Impact Analysis
Question 5
An office building receives an ENERGY STAR score of 82 using validated property and energy data. The owner asks what that result establishes. Select the defensible interpretation.
Show answer & explanation
Correct answer: D - It exceeds the 75-point certification threshold, but certification still requires additional verification.
Question 6
A facility used 1,200 MWh before recommissioning and 1,080 MWh during the reporting year. The owner calls this a 10% energy saving. However, the accepted baseline model predicts 1,000 MWh without the improvements under the reporting year's weather and occupancy. Metering boundaries are unchanged. What result belongs in the measurement-and-verification finding?
Show answer & explanation
Correct answer: C - An 80 MWh increase relative to the adjusted baseline, not a verified saving.
Question 7
A previously commissioned office building now houses a round-the-clock operations center. Staff have overridden the original weekday schedules to support the new use. The owner commissions an investigation, correction of operating problems, and verification of performance. Which scope fits both the building's history and its present needs?
Show answer & explanation
Correct answer: A - Recommissioning against owner-approved Current Facility Requirements that reflect the new operating needs.
Domain 4: Business Continuity Strategies
Question 8
An air-handling unit is economizing with outdoor air at 50°F and return air at 74°F. The BAS requests full outdoor air from its linked outdoor/return dampers, yet the well-mixed air upstream of the coils remains at 72°F. Independent measurements confirm the temperatures; no heat source lies between the intake and the mixed-air measurement. Which fault most directly explains the findings?
Show answer & explanation
Correct answer: A - A disconnected mixing-damper linkage leaves the blades in their minimum-outdoor-air position.
Question 9
During an occupied building's commissioning visit, a technician stops a supply fan through the building automation system and prepares to remove its belt guard to adjust belt tension. The fan has stopped rotating, but its variable-frequency drive remains energized and no lockout has been applied. Before access to the belt drive, the commissioning provider should insist on:
Show answer & explanation
Correct answer: D - Authorized isolation and lockout of hazardous energy, stored-energy control, and verification before access.
Question 10
A 120-ton chiller is being tested at a specified part-load condition. The acceptance criterion is no more than 0.80 kW/ton for the chiller package alone, excluding external pumps. Stabilized measurements are 200 US gpm of water, 54°F entering, 44°F leaving, 60 kW at the chiller feeder, and 12 kW at the separate pump feeder. Use cooling output = 500 × gpm × temperature difference in °F, in Btu/h, and 12,000 Btu/h per ton. Which result evaluates the specified criterion correctly?
Show answer & explanation
Correct answer: A - 0.72 kW/ton; the chiller package meets the criterion.